This version contains a number of minor updates as detailed in the release notes.
There is an upgrade to the completion calculation, adding in a downtime percent adjustment to the calculation. To come up with the completion date, CheckPoint first works out the average production to date in the survey. Then, using the remaining preplot km, this average is used to compute the number of days the remaining production will take to complete. This value is then adjusted by the new percent value, and the additional production days added on to come up with the end of production estimate.